7 men can dig a canal in 14 weeks. After 2 weeks of work another 7 men joined them in how many weeks more will the work be finished?
asked
Oct 6, 2021
2.0k
views
3
votes
7 men can dig a canal in 14 weeks. After 2 weeks of work another 7 men joined them in how many weeks more will the work be finished?
Mathematics
college
VinuBibin
asked
by
VinuBibin
7.1k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
Answer:
1 week
Explanation:
Szymon Maszke
answered
Oct 12, 2021
by
Szymon Maszke
8.6k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
No related questions found
Ask a Question
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.
Categories
All categories
Mathematics
(3.7m)
History
(955k)
English
(903k)
Biology
(716k)
Chemistry
(440k)
Physics
(405k)
Social Studies
(564k)
Advanced Placement
(27.5k)
SAT
(19.1k)
Geography
(146k)
Health
(283k)
Arts
(107k)
Business
(468k)
Computers & Tech
(195k)
French
(33.9k)
German
(4.9k)
Spanish
(174k)
Medicine
(125k)
Law
(53.4k)
Engineering
(74.2k)
Other Questions
How do you can you solve this problem 37 + y = 87; y =
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qamnty