asked 97.0k views
5 votes
The Green Corporation has 10,000 square feet of tile in their warehouse. Each day of manufacturing adds 1,250 square feet of tile to the warehouse. If the Green Company needs 20,000 square feet of tile for a large order, how many days will it take before the warehouse can fill this order?

asked
User Tomek
by
7.0k points

1 Answer

2 votes

Answer:

8 days

Explanation:

20,000-10,000=10,000

10,000/1,250= 8

so it would take 8 days

answered
User Dmitry Mina
by
7.9k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.