A construction worker estimates that a kitchen will take 1 Person 200 hours. If 5 people work on the job for 8 hours a day, how many days will it take for them to complete the job?

A) 4

B) 5

C) 6

D) 7

asked
User Sansh
by
8.6k points

1 Answer

2 votes

Answer:

the answer it 5 also my proff is on Google