asked 85.1k views
0 votes
Monica, a project manager at a software firm, learns during a status report meeting that a difference exists between the baseline scope and the actual project performance. What does Monica need to do next?

asked
User Bananas
by
8.3k points

1 Answer

7 votes

Answer:

Analyze the variance

Step-by-step explanation:

In a situation like this, it is expected that the project manager identifies the differences or variance which exists between the baseline scope and actual project performance. It is however when the variance has been analyzed, then the project manager can conclude whether a change in scope is needed or not.

Hence, in this case, what Monica need to do next is to ANALYSE THE VARIANCE

answered
User Msuchy
by
8.7k points