A painter can finish painting a house in 7 hours. Her assistant takes 9 hours to finish the same job. How long would it take for them to complete the job if they were working together? Group of answer choices

asked
User Lahiru
by
7.6k points

1 Answer

7 votes

Answer:

x=3 15/16 hours together

Explanation:

the painter paints 1/7 of the house in 1 hour

the assistant paints 1/9 of the house in 1 hour

x=# of hours it takes them together to paint the house

(1/7)x+(1/9)x=1 (job finished)

multiply both sides by the LCM which is 63

63(1/7)x+63(1/9)x=63(1)

9x+7x=63

16x=63

x=63/16

x=3 15/16 hours together