It takes 20 men 60 days to complete a building work.How many days longer will It take 15 men, assuming they work all work at the same rate?
asked
May 11, 2021
122k
views
0
votes
It takes 20 men 60 days to complete a building work.How many days longer will It take 15 men, assuming they work all work at the same rate?
Mathematics
high-school
Aaron Jones
asked
by
Aaron Jones
7.9k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
5
votes
Answer:
80days
Explanation:
20m=60days
15m(will take
m
o
r
e
d
a
y
s
)
2
0
÷
1
5
×
6
0
= 80 days
Shanethehat
answered
May 16, 2021
by
Shanethehat
7.9k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
← Prev Question
Next Question →
No related questions found
Ask a Question
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.
Categories
All categories
Mathematics
(3.7m)
History
(955k)
English
(903k)
Biology
(716k)
Chemistry
(440k)
Physics
(405k)
Social Studies
(564k)
Advanced Placement
(27.5k)
SAT
(19.1k)
Geography
(146k)
Health
(283k)
Arts
(107k)
Business
(468k)
Computers & Tech
(195k)
French
(33.9k)
German
(4.9k)
Spanish
(174k)
Medicine
(125k)
Law
(53.4k)
Engineering
(74.2k)
Other Questions
How do you can you solve this problem 37 + y = 87; y =
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search Qamnty