"A city project to build a soccer complex with six fields Is in the planning phase of the project life cycle. One of the project team members shares details from a project he worked on to build two soccer fields completed a year ago." Which estimation method should the project team use for the new project?

a. Template
b. Ratio
c. Top-down
d. Bottom-up

asked
User Ahmaad
by
7.3k points

1 Answer

0 votes

Answer:

a. Template

Step-by-step explanation:

A template of the previous soccer fields that have been previously constructed should be used in the planning of the soceer fields that are about to be built.

Certain adjustments should be made to the template to account for differences.