Project risk is lowest during the: Finish phase of the project life cycle. Conceive phase of the project life cycle. Develop phase of the project life cycle. Execute phase of the project life cycle.

1 Answer

5 votes

Answer:

Finish phase of the project life cycle.

Step-by-step explanation:

The finish phase (or termination, or completion phase) of a project life cycle is basically when the project is completed and it is being delivered to the customer. Depending on the project, paperwork and documents are handed out to the customer, contracts with workers and suppliers are terminated. Everyone involved with the project must be notified about its completion and all obligations are paid for.