asked 158k views
3 votes
Company purchased a tract of land for $4,500,000 in anticipation of extracting 1,425,000 tons of ore. The residual value of the land is expected to be $480,000. The company mines 125,000 tons of ore in the first yearWhat is the unit depletion rate? (Round to the nearest $0.01.)a $3.16 b. $3.00 c. $3.50 d. $2.82

asked
User Moberg
by
8.2k points

1 Answer

5 votes
77777777777777777776666666677
answered
User Vicktoria
by
8.2k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.