Four workers finish some work in 90 minutes. How much time it will take six workers to finish same work

1 Answer

1 vote

Answer:

135 minutes.

Explanation:

Let's use a ratio:

workers : minutes

4 : 90

1 : 22.5

6 : 135

It will take them 135 minutes (it seems wrong but...)