Jeremy Corporation estimated manufacturing overhead costs for the year to be $ 550 comma 000. Jeremy also estimated 8 comma 000 machine hours and 3 comma 000 direct labor hours for the year. It bases the predetermined overhead allocation rate on machine hours. On January​ 31, Job 25 was completed. It required 5 machine hours and 1 direct labor hours. What is the amount of manufacturing overhead allocated to the completed​ job?

asked
User Nubcase
by
8.5k points

1 Answer

1 vote

Answer:

$343.75

Step-by-step explanation:

The computation of amount of manufacturing overhead is shown below:-

For computing the amount of manufacturing overhead first we need to find out the predetermined overhead rate which is shown below:-

Predetermined overhead rate = Estimated manufacturing overhead costs ÷ Estimated machine hours

= $550,000 ÷ 8,000

= $68.75 per machine hour

Overhead allocated = Predetermined overhead rate × Machine hours

= $68.75 × 5

= $343.75