asked 33.2k views
5 votes
Your project is significantly over budget and behind schedule. It is critical that you determine your projected duration. To gain a better understanding of the project you analyze the sequence of deliverables, activities or tasks to find the ones with the least amount of schedule flexibility. What technique are you using

1 Answer

2 votes

Answer:

CPM (Critical Path Method) technique

Step-by-step explanation:

Critical Path Method is the sequence of project network activities that add up to the longest overall duration.

Using four required inputs, it calculates the longest path of planned activities to logical end points, to the end of a project and the earliest and latest that each activity can start and finish without making the project longer. Also determines what can be delayed without making the project longer.

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.