In the early stages of planning, the project planner should attempt to specify completion dates only for major employees within the project. _________________________

1 Answer

5 votes

Answer:

False

Step-by-step explanation:

In the early stages of planning, the project planner should attempt to specify completion dates only for major milestones within the project and not employees. Specifying major milestones or events during the course of the project will help in monitoring the progress of the project and to check whether the team is on track to meet the project deadline.