asked 51.0k views
2 votes
In the following Earliest Start Time (EST) graph, assume each unit of time is an hour.

How long does it take to do just task E?



4

6

8

14

In the following Earliest Start Time (EST) graph, assume each unit of time is an hour-example-1

1 Answer

1 vote

8

Explanation:

  • Critical Path Analysis is presented using the circle and arrow diagrams.
  • Earliest Start Time = the earliest possible time of starting the activity
  • An arrow running between two event circles shows the activity needed to complete that task.
  • All arrows run left to right
  • Time for doing just task E = 8 hours (as shown in the figure)

answered
User Andre Araujo
by
7.6k points

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.