asked 48.2k views
5 votes
Six men working 8 hours a day dig a shamba in 5 days. How many more days will it take 4 men working 8 hours a day to finish the job?

NOTE:PLEASE EXPLAIN IN DETAIL !!!

asked
User Lib
by
7.5k points

1 Answer

0 votes

6m=40hours

1m=40×6h

=240hours

4m=240÷4

=60 hours

divide 60 by 8

=7.5 days

thus,

4 men take 2 and 1/2 day more to complete the job.

Answer: 2 1/2days