asked 107k views
4 votes
A company calculated the predetermined overhead based on an estimated overhead of $70,000, and the activity for the cost driver was estimated as 2,500 hours. If Product A utilized 1,350 hours and Product B utilized 1,100 hours, what was the amount of overhead assigned to the products

asked
User Xlson
by
8.2k points

1 Answer

5 votes

Answer:

$68,600

Step-by-step explanation:

Activity Based Overhead Rates = Estimated Overhead / Expected Use of Cost Drivers per Activity (Hours)

Activity Based Overhead Rates = $70,000 / 2,500

Activity Based Overhead Rates = $28

Overhead Assigned = Overhead Rate * Hours Utilized

Product A Overhead Assigned = $28 * 1,350 hours

Product A Overhead Assigned = $37,800

Product B Overhead Assigned = $28 * 1,100 hours

Product B Overhead Assigned = $30,800

Total Overhead Assigned = Product A Overhead Assigned + Product B Overhead Assigned

Total Overhead Assigned = $37,800 + $30,800

Total Overhead Assigned = $68,600

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.