Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 12.6 Process time 1.7 Inspection time 0.9 Move time 4.3 Queue time 6.0 The delivery cycle time was:

asked
User Kenzi
by
8.0k points

1 Answer

4 votes

Answer:

25.5 hours

Explanation:

Delivery cycle time is the time span from when an order is made by a customer and the time the order is delivered to the customer.

Delivery cycle time = Wait time + Move time + Queue time + Process time + Inspection time

12.6 + 4.3 + 6.0 + 1.7 + 0.9 = 25.5