It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

asked
User Tokabi
by
8.3k points

1 Answer

2 votes

Answer:

20 days

Explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job