asked 92.9k views
4 votes
CPU-on-Demand (CPUD) offers real-time high-performance computing services. CPUD owns 1 supercomputer that can be accessed through the Internet. Their customers send jobs that arrive on average every 5 hours. The standard deviation of the interarrival times is 5 hours. Executing each job takes on average 3 hours on the supercomputer and the standard deviation of the processing time is 4.5 hours. How long does the customer have to wait to have the job completed?

1 Answer

4 votes

Answer:

61 hours