A construction company can remove 8 1/4 metric tons of dirt from a construction site in 5 1/2 hours what is the unit rate in metric tons per hour?

asked
User Xu Hui
by
7.5k points

1 Answer

1 vote

Answer:

1 1/2 tons per hour

Explanation:

8 1/4 ÷ 5 1/2