asked 211k views
2 votes
A takes 6 days less than B to finish a piece of work. If both A and B together can finish the work in 4 days, find the time taken by B to finish the work.

2 Answers

12 votes

Please find attached herewith the solution of your question.

Hope it helps.

A takes 6 days less than B to finish a piece of work. If both A and B together can-example-1
answered
User Martin Cook
by
7.9k points
3 votes

Answer:

If both A and B together can finish it in 4 days, how many days will B take to finish the work? ⇒x=12 or x = 2 x cannot be less than 6. Therefore, B also can finish the work in 12 days.

Hope You Enjoy !

Explanation:

No related questions found

Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.