asked 29.2k views
2 votes
PERT, but not CPM, has the ability to consider the precedence relationships in a project. True False

1 Answer

6 votes

False is the answer.

Hope you have a great day :)

answered
User NIlesh Sharma
by
7.9k points

Related questions

asked Nov 2, 2024 169k views
Sherod asked Nov 2, 2024
by Sherod
8.1k points
1 answer
3 votes
169k views
asked Jan 22, 2024 65.4k views
Bernardo Vale asked Jan 22, 2024
by Bernardo Vale
6.9k points
1 answer
2 votes
65.4k views
asked Jul 11, 2024 112k views
Sinstein asked Jul 11, 2024
by Sinstein
8.5k points
1 answer
5 votes
112k views
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.