..Paul takes 8 hours to complete a job or 1/8 of work per hour
and Lisa takes 10 hours to complete the same job. i.e. 1/10 of work per hour
if they both work together, they do 1/8+1/10 = 9/40 of the work per hour
how long will it take them to complete the job:
1 = all the time, they do 9/40 of the work per hour
time taken: 1:(9/40)= (1*40)/9=4.4444hd approximately 4h26min