Answer:
Explanation:
Given:
8 machines would take 19 hours to produce 1000 bolts
- machine and hour are direct proportional to bolts
- machine is inverse proportional to hour
machine₁ × hour₁ = machine₂ × hour₂
8 × 19 = 17 × hour₂
hour₂ = 8 × 19 ÷ 17
= 8.94 hrs → less than 9 hours