(True/False): The portion of the master production schedule farthest into the future is often frozen to reduce forecasting requirements.

asked
User Thesonix
by
8.3k points

1 Answer

4 votes

Answer:

True

Step-by-step explanation:

The statement is true. In master production scheduling, the portion of the schedule farthest into the future (usually 6-12 months out) is often frozen. This means the forecasted requirements for that period are fixed and not changed frequently.