Answer:
The designed capacity of the plant is 86,400 soaps per week (360 soaps/hour x 8 hours/shift x 3 shifts/day x 7 days/week). The capacity utilization last week was 40.5% (35,000 units / 86,400 units). The efficiency last week was 47.4% (35,000 units / (0.75 x 86,400 units)).
Step-by-step explanation: