asked 95.5k views
5 votes
A project will take a total of 720 person-days to complete. If the project must be completed in 30 days, how many people must be employed? PLEASE HURRY

2 Answers

6 votes
It’s 24!! EXPLAIN-720/30=24 because you have to divide the amount of people by days p/d= e
answered
User Jacob King
by
8.4k points
3 votes

Answer:

192 hours per day / 8 hours per person per day = 24 people

Explanation:

Assuming each person works for 8 hours a day, the total number of hours needed to complete the project is:

720 person-days x 8 hours = 5,760 hours

To complete the project in 30 days, the total number of hours needed per day is:

5,760 hours / 30 days = 192 hours per day

answered
User Simon Duff
by
8.3k points