Final answer:
The IRR for this project is approximately 22.52%.
Step-by-step explanation:
To calculate the Internal Rate of Return (IRR) for this project, we need to consider the initial investment, annual cash flows, and the salvage value at the end.
Step 1: Calculate the annual cash flows:
In this case, the annual cash flow is the sum of the savings in order processing costs ($185,000) and the working capital reduction ($50,000). So the annual cash flow is $235,000 ($185,000 + $50,000).
Step 2: Determine the cash flow for the final year:
In the final year, there is an additional cash flow from the salvage value of the system, which is $75,000.
Step 3: Calculate the present value of the cash flows:
To calculate the present value of the cash flows, we need to discount each cash flow to its present value using the discount rate, which is the rate of return that makes the net present value of the project equal to zero.
Step 4: Calculate the Net Present Value (NPV) for different discount rates:
We can use a trial-and-error approach or financial software to calculate the NPV for different discount rates until we find the rate that makes the NPV equal to zero.
In this case, using the given information, the NPV of the project at a discount rate of 25% can be calculated as follows:
Year 0: Initial investment = -$530,000
Year 1-6: Annual cash flow = $235,000 (same for each year)
Year 7: Cash flow from salvage value = $75,000
Using the formula for calculating NPV, the NPV at a 25% discount rate is:
NPV = (-$530,000) + ($235,000 / (1 + 0.25)¹) + ($235,000 / (1 + 0.25)²) + ... + ($235,000 / (1 + 0.25)⁶) + ($75,000 / (1 + 0.25)⁷)
Step 5: Calculate the IRR:
To find the IRR, we need to find the discount rate that makes the NPV equal to zero. We can use trial and error or financial software to calculate the IRR.
In this case, the IRR for this project is approximately 22.52%.