A poorly written scope statement will have little effect on time or cost estimates. True or false?

asked
User Stu Cox
by
8.2k points

1 Answer

4 votes

Answer: False.

Step-by-step explanation:

A poorly written scope statement can have a significant impact on time and cost estimates as it may lead to misunderstandings, ambiguity, and incomplete requirements, resulting in project delays, rework, and additional expenses.