asked 174k views
1 vote
Which of the following best describes the approach for determining the Sprint length?

Select one:
a. Sprint should always be 30 days
b. Sprint should always be two weeks
c. The team determines Sprint length by dividing the total number of story points by the average velocity of the team
d. The team should agree on the length of the Sprint, taking the size and complexity of the project into consideration

1 Answer

5 votes

Final answer:

The team should agree on the length of the Sprint, taking the size and complexity of the project into consideration. Sprints are commonly two weeks long.

Step-by-step explanation:

The correct approach for determining the Sprint length in Agile project management is option d: The team should agree on the length of the Sprint, taking the size and complexity of the project into consideration.

The Sprint length is typically determined through collaborative decision-making by the project team. The team should consider factors such as project complexity, team capacity, and the organization's goals and constraints.

The Sprint length can vary based on the nature of the project, but a common practice is to have Sprints of two weeks duration. This allows for iterative development and frequent feedback.

No related questions found