Answer:
Total time taken = 0.769 hour 
Step-by-step explanation:
using the velocity method 
for sheet flow ; 
Tt = 
 
 
Tt = travel time 
n = manning CaH
Pl = 25years
L = how length ( ft )
s = slope
For Location ( 1 )
s = 0.045 
L = 1000 ft
n = 0.06 ( from manning's coefficient table ) 
Tt1 = 0.128 hour 
For Location ( 2 ) 
s = 2.5 %
L= 750
n = 0.13 
Tt2 = 0.239 hour
For Location ( 3 ) 
s = 1.5% 
L = 500 ft 
n = 0.15 
Tt3 = 0.237 hour
For Location (4) 
s = 0.5 %
L = 250 ft
n = 0.011
Tt4 = 0.165 hour 
hence the Total time taken = Tt1 + Tt2 + Tt3 + Tt4 
 = 0.128 + 0.239 + 0.237 + 0.165 = 0.769 hour