Where deviations from the drawings are warranted, what action should the inspector take?

a) Authorize approval of the changes.
b) Obtain official approval for the changes.
c) Reject the work without any further consideration.
d) Stop the work until drawing revisions have been completed.

asked
User KeithS
by
8.0k points

1 Answer

4 votes

Final answer:

The inspector should obtain official approval for any warranted deviations from the drawings through a formal Change Order.

Step-by-step explanation:

When deviations from the drawings are warranted, the action the inspector should take is to obtain official approval for the changes. It is not within the inspector's authority to authorize approval of changes on their own. Instead, the inspector must ensure that any amendments to the original plan have been documented and sanctioned through official channels, typically involving the project's architect, engineer, or other responsible parties within the scope of the contract. Rejecting the work without consideration or stopping work indefinitely are not professional responses unless the deviations pose immediate safety or structural concerns. The process often involves submitting a formal Change Order request to the project management team for review and approval.