The calculated schedule variance on your project is $8,000. Last month it was $10,000, and the month previous it was $18,000. Which statement is most accurate?

1) The project is trending under-budget
2) The project is trending behind of schedule
3) The project is trending ahead of schedule
4) The project is trending over budget

asked
User Rfanatic
by
8.7k points

1 Answer

3 votes

Final answer:

The most accurate statement is that the project is trending behind schedule. Schedule variance provides information on the timeliness of a project's progress, not the budget. The gradual decrease in schedule variance highlights that the project's pace is slowing.

Step-by-step explanation:

The question pertains to project management, specifically schedule variance and its trend over time. Schedule variance is a measure of schedule performance on a project. If the schedule variance is positive, it indicates that the project is ahead of schedule. Conversely, a negative schedule variance indicates that the project is behind schedule. Since the schedule variance has decreased from $18,000 to $10,000, and then to $8,000, this implies that the project is being completed more slowly than planned. This decrease in the variance amount does not suggest an under-budget or over-budget situation, but instead a delayed one.

Therefore, the most accurate statement is: (2) The project is trending behind schedule.

It's important to note that budget and schedule are two separate aspects of project performance measurement. Schedule variance speaks to time-related performance, while cost variance would be the indicator of budgetary performance.