What is the quantity of work done when a crane lifts a 100-N block from 2 m above the ground to 6 m above the ground?

A. 100 J
B. 200 J
C. 400 J
D. 600 J

asked
User Haynar
by
8.2k points

2 Answers

9 votes

Answer:

400j

Explanation:

answered
User Doublehelix
by
8.4k points
6 votes
The correct answer would be

C. 400 J