asked 75.2k views
4 votes
If a man works for 8 hours a day, he can finish a job in 12 days. How many hours per day must he work to complete it in 10 days?

asked
User Wicke
by
7.3k points

2 Answers

3 votes

Answer:

6.67 hour per day

Explanation:

If

=8 hours a day = 12 days

then

= ? = 10 days

= 10/12 × 8hours per

= 6.67 hours per day.

answered
User Sheo Dayal Singh
by
7.7k points
7 votes

Answer:

9.6 hours

Explanation:

12×8 would equal the amount of hours it takes to complete the job in 12 days so you simply divide that number by 10 which will give you 9.6h