Project managers must manage the __________, which consists of all tasks that must start and finish on schedule or the project will be delayed unless corrective action is taken.

asked
User Dinigo
by
8.8k points

1 Answer

4 votes
Project managers must manage the Critical Path which consists of all tasks that must start and finish on schedule or the project will be delayed unless corrective action is taken.