A project objective such as "complete the project" is too ambiguous because the customer and the contractor may have ______________of what is meant by "complete."

asked
User JBecker
by
7.5k points

1 Answer

6 votes
The customer and the contractor may have different views of what is meant by the word "complete". Compete the house, refers to the structural and floor plans prepared to be finished by a specific time. Completing the house, refers to completing the floor plan given. 