Under management by exception, which differences between planned and actual results should be investigated? material and noncontrollable controllable and noncontrollable material and controllable all differences should be investigated

asked
User Whlk
by
8.5k points

1 Answer

3 votes

Please correctly type the given choices next time since they are jumbled. I believe the correct choices are:

a. material and noncontrollable

b. controllable and noncontrollable

c. material and controllable

d. all differences should be investigated

The correct answer from the choices above is C.

Answer:

material and controllable