A construction company builds a concrete ramp as shown. What volume of concrete is needed to form the ramp?

360 cubic feet
600 cubic feet
700 cubic feet
720 cubic feet

A construction company builds a concrete ramp as shown. What volume of concrete is-example-1
asked
User Gauranga
by
8.2k points

2 Answers

3 votes

I think it's 360 cubic feet

answered
User DrC
by
8.5k points
5 votes

10 x 12 x 6 = 720

720/2 = 360 cubic feet needed