"To define activities, the project team should start with reviewing the schedule management plan, scope baseline, enterprise environmental factors, and organizational processes"

A. True
B. False

asked
User Mtalexan
by
8.2k points

1 Answer

4 votes

Answer: True

Explanation: Activities in project management are the steps to achieve the purpose of the project ,there are called project deliverables. In order to define them, organizational processes has to be reviewed such that it matched the schedule management, from there they can come up with a plan, evaluate the enterprise environmental factors and set a scope baseline, so yes it is true.