asked 179k views
4 votes
Stiviko's approved work plan included 4 technicians to create 200 web pages

over 5 days. What was the unit metric for the production work?

2 Answers

4 votes

Answer:

10 pages per technician per day

Explanation:

answered
User Wuliwong
by
8.4k points
5 votes

Answer:

10 pages per technician per day is the unit metric for the production work.

Explanation:

Consider the provided information.

Stiviko's approved work plan included 4 technicians to create 200 web pages over 5 days.

They can create 200 web pages over 5 days.


(200)/(5)=40

That means in one day they can create 40 pages.

There are 4 technicians who work, therefore the unit metric for the production work is:
(40)/(4)=10

Hence, 10 pages per technician per day is the unit metric for the production work.

answered
User Jjxtra
by
7.4k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.