If you are expected to complete 2% of the course each day and you don’t do the work, how many days will you have until you reach 35% behind?

asked
User SiddP
by
8.3k points

1 Answer

1 vote

Answer:

17.5 days

Explanation:

First take 35% and divide it by 2%


35 / 2 = 17.5