Many organizations require the completion of a project close-out report upon completion of a project. These reports typically include _____________.

asked
User Splitusa
by
8.3k points

1 Answer

5 votes

Answer:

The correct answer is a review of the project's original justification.

Step-by-step explanation:

You should refer to this section, which identifies and explains the different ways to solve the problem. It is a qualitative expression about why we should start a certain project, why it is worth it and what will be its scope or impact on its socio-economic environment.