A work element in a manual assembly task consists of the following MTM-1 elements: (1) R16C, (2) G4A, (3) M10B5, (4) RL1, (5) R14B, (6) G1B, (7) M8C3, (8) P1NSE, and (9) RL1.

(a) Determine the normal times in TMUs for these motion elements.
(b) What is the total time for this work element in sec

asked
User Khalia
by
7.8k points

1 Answer

3 votes

Answer:

a)

1) R16C ; Tn = 17 TMU

2) G4A ; Tn = 7.3 TMU

3) M10B5 ; Tn = 15.1 TMU

4) RL1 ; Tn = 2 TMU

5) R14B ; Tn = 14.4 TMU

6) G1B ; Tn = 3.5 TMU

7) M8C3 ; Tn = 14.7 TMU

8) P1NSE ; Tn = 10.4 TMU

9) RL1 ; Tn = 2 TMU

b) 3.1 secs

Step-by-step explanation:

a) Determine the normal times in TMUs for these motion elements

1) R16C ; Tn = 17 TMU

2) G4A ; Tn = 7.3 TMU

3) M10B5 ; Tn = 15.1 TMU

4) RL1 ; Tn = 2 TMU

5) R14B ; Tn = 14.4 TMU

6) G1B ; Tn = 3.5 TMU

7) M8C3 ; Tn = 14.7 TMU

8) P1NSE ; Tn = 10.4 TMU

9) RL1 ; Tn = 2 TMU

b ) Determine the total time for this work element in seconds

first we have to determine the total TMU = ∑ TMU = 86.4 TMU

note ; 1 TMU = 0.036 seconds

hence the total time for the work in seconds = 86.4 * 0.036 = 3.1 seconds