When multiple architects work on a construction plan, which section of a construction plan will help them keep track of when the changes are made and by whom?

A.
framing plan
B.
schedule
C.
title block
D.
bill of materials

1 Answer

3 votes

Answer:

the answer is schedule!!!

Step-by-step explanation: