1. Generally speaking, the lowest level in the WBS is referred to as: A. Level 3 B. Level 4 C. Level 5 D. The work package

asked
User Eddd
by
7.7k points

1 Answer

5 votes

Answer:

D)The work package

Step-by-step explanation:

WBS(work breakdown structure) helps to bring down the project scope to deliverables, it can be applied to tasks, project as well as programs. It defines, and bring about organization of the work. WBS has different levels and each level is unique, with the highest level having "project ultimate goal" follow by another level of "project objectives" follows by another level of project outputs and activities. Generally speaking, the lowest level in the WBS is referred to as work package. work package are also known as "terminal element"of a WBS whereby the deliverables is been decomposed to different components.

answered
User Steven Behnke
by
7.8k points
Welcome to Qamnty — a place to ask, share, and grow together. Join our community and get real answers from real people.