An individual is coding 8 new functions to be used in a digital sales document for a company. The individual estimates that most of the functions will take 10 minutes each to create, but the last two functions will take 25 minutes each. How long should it take for the individual to complete all 8 functions

asked
User Wesley
by
7.9k points

1 Answer

1 vote

Answer:

1
(5)/(6) hours (110 minutes).

Explanation:

The individual want to code 8 new functions of which most of the functions will take 10 minutes each to create, but the last two 25 minutes.

Thus, 6 of the 8 new functions would take 10 minutes, while two will take 25 minutes. So that;

6 x 10 minutes = 60 minutes

But for the last two;

2 x 25 minutes = 50 minutes

Total time required = (60 + 50) minutes

= 110 minutes

= 1
(5)/(6) hours

The estimated time to complete all 8 functions is 1
(5)/(6) hours (110 minutes).