Forty five men can construct a road 210m long in 60 days. What length would be constructed by 72 men in 50 days assuming that all work at the same rate?

asked
User Frist
by
8.0k points

1 Answer

5 votes

Answer:

280m

Explanation:

Work rate would be (210m)/(45people)(60days)=7/90 m/(people)(day)

7/90 m/(people)(day) * 72people * 50days =280m