Spruce Inc. completed Job No. A20 during 2020. The job cost sheet listed the following: Job No. A20 Costs for 5000 units produced: Direct materials $30,000 Direct labor $45,000 Manufacturing overhead applied $20,000 Units sold 2,000 units How much is the cost of the finished goods on hand at the end of the period from this job?

asked
User Kenric
by
8.0k points

1 Answer

4 votes

Answer: $57,000

Step-by-step explanation:

Cost of finished goods on hand at end of period = Goods on hand * Unit Cost

Goods on hand = Units Produced - Units sold

= 5,000 - 2,000

= 3,000 units

Unit Cost = Total Cost / Units Produced

= ( Direct materials + Direct Labor + Manufacturing overhead)/ Units produced

= ( 30,000 + 45,000 + 20,000) / 5,000

= $19

Cost of finished goods on hand at end of period = 3,000 * 19

= $57,000