Prime Cost and Conversion Cost Benton Engineering Services Company incurred the following during 2019:

Direct labor $60,000
Overhead 110,000
Selling expenses 56,000
Administrative expenses 95,000
Calculate prime cost and conversion cost for Benton Engineering Services Company during 2019.

asked
User Quasaur
by
8.7k points

1 Answer

4 votes

Answer:

Prime cost is $60,000

And, the conversion cost is $170,000

Step-by-step explanation:

The computation of the prime cost and the conversion cost is shown below:

Prime cost is

= Direct material + Direct labor

= $0 + $60,000

= $60,000

And,

Conversion cost = Direct labor + Overhead

= $60,000 + $110,000

= $170,000